We had a LONG delay (3 weeks) in progress on the pool due to the Christmas and New Year holidays.

Finally, a return to working on the pool. Two men worked on and completed the coping and tiles this nice Sunday,  January 11th!

 

Installation of the bull-nosed coping bricks around the perimeter of the pool.